US Data Center Construction Fell Amid Permit and Power Delays

A data center under construction in Abilene, Texas.Photographer: Kyle Grillot/Bloomberg

Construction of new data centers in the US fell for the first time since 2020 despite soaring demand for artificial intelligence computing capacity, as developers face delays in permitting, zoning and power procurement.

Capacity under construction fell to 5.99 gigawatts at the end of 2025 from 6.35 gigawatts at the end of 2024, real estate brokerage CBRE Group Inc. reported Wednesday.